Corporate Office Construction - Clayco - Citigroup – Tuscon

Citigroup – Tucson

Project Description

Clayco completed the renovation of an existing building for Citigroup in Tucson. The 110,000-square-foot, two-story building was converted into a call center on the University of Arizona’s campus. The renovation included entrance finishes, new break rooms and bathrooms, a UPS room, tech rooms and modified MEP FP systems. Raised access floors extend throughout the lobby and the exterior was constructed of metal panes and glass.

Clayco completed the structure in just eight months by working six day weeks with two 10-hour shifts and one shift on Sundays. Clayco’s team also installed new rooftop air conditioner units, new ductwork, and electrical piping to the penthouse.